Project Description:
New security fencing along Segovia Way and Benita Drive,
new landscape at front of campus, new student gathering
areas at drop off zones, upgrades to bus loading area,
increase staff parking, reconfigure primary student
playground, new student drop-off/pick-up area, new
playground equipment, remodel administration building,
relocate nurses room, provide nurse’s restroom, remodel
teacher’s workroom, design a more secure front lobby,
provide more storage, remodel restrooms, relocate
principal’s office, provide office space, upgrade light
fixtures and low voltage systems, remodel library
building, create new learning resource center with
library/computer lab combination, provide new office and
teaching spaces for speech, Psychologist, RSP, Bilingual
Aides, Parent Coordinator and Title 1, remodel girls and
boys restrooms for ADA accessibility, remodel
Multi-purpose, provide more space in existing
Multi-purpose, build new stage area and conference room,
replace intrusion alarm system with new addressable
system, repairs and upgrades to campus common areas,
repairs to ball fields, move Band room to other side of
campus to accommodate new parent drop off.
Project Funding: The project construction cost
is
$2,000,000 and is funded from Measure N.
Project Timeline: The project began in
April 2008 and is scheduled to be complete by September 2008.
Project
Before Pictures:
April 1, 2008
Project Progress Pictures:
March 26, 2008
April 9, 2008
May 6, 2008
May 20, 2008
June 3, 2008
June 10, 2008
June 25, 2008
July 7, 2008
July 16, 2008
September 3, 2008
September 17, 2008