Project Description:
Installation of casework; conversion of mechanical rooms
to storage and custodial office space; installation of
raceway for future computer lab; installation of cable
television infrastructure; replacement of sink in
cafeteria custodial room; addition of walkways around
the administration building; installation of new fencing
around K Building and along Benita; installation of a
new master clock; replacement of door and hardware where
needed; remodel and reconfiguration of E-wing;
renovation of food services storage; replacement of food
services sink; renovation of the nurse’s office and
staff room; and installation of a new band room
relocatable building.
Project Funding: The project construction cost was
$975,000 and was funded from Measure B.
Project Timeline: The project began in
June 2004 and was complete by September 2004.
Project Progress Pictures:
June 25, 2004
July 26, 2004
July 28, 2004
August 25, 2004
February 20, 2007