Project Description:
Included HVAC, replacement of interior
finishes including floors, wall surfaces and ceilings;
installation of new equipment including white boards,
casework and cabinets; upgrades to toilet rooms
including accessibility, toilets, sinks and partitions;
accessibility upgrades for ADA compliance; replacement
of exterior doors and all hardware; repair and/or
replacement of roofs as needed; upgrade of electrical
system and increase in power capacity in classrooms to
accommodate technology; complete technology data system
including conduit, trenching, cabling and active
hardware, increase network speed; provide computers and
laser printers; installation of new signal systems,
including telephone, intercom, clocks, bells, fire alarm
and intrusion alarm; installation of new energy
efficient lighting fixtures and controls; repair of dry
rot and termite damage; asbestos abatement; and
replacement of old furniture.
Project Funding:
The project construction cost was
$3.1 million and was funded from Measure C and the state school building
program.
Project Timeline:
The project began in May 2002 and was complete by December 2002.
Project Progress Pictures:
May 2, 2002
July 2, 2002
July 10, 2002
July 22, 2002
August
16, 2002
August
20, 2002
August
22, 2002
September 5, 2002
September 10, 2002
October 1, 2002
October 22, 2002