Project Description: Includes
conversion of Wing G to a cafeteria annex and art room
and refurbishment of existing kitchen and multipurpose
room with removal of stage and replacement of flooring.
Project Funding:
The project construction cost was
$1.45 million and was funded from Measure C and the state school building
program.
Project Timeline:
The project began in May 2002 and was complete by January 2003.
Pictures of Work in Progress:
Demolition - June 18, 2002
July 8,
2002
July 16,
2002
July 23,
2002
July 30,
2002
August 6,
2002
August 16,
2002
September 3,
2002
September 10,
2002
October 1,
2002
September 24, 2004