Project Description: This
project included the construction of 25 classrooms,
learning resource center, multipurpose room and
administration.
Project Funding:
The project construction cost was
$10.8 million and was funded from Measure C and the state school building
program.
Project Timeline:
The project began in May 2002 and was complete by July 2003.
Pictures of Work in Progress:
Groundbreaking Pictures
Site Work Begins - May 5, 2002
June 19, 2002.
June 26, 2002
July 10, 2002
July 18, 2002
July 24, 2002
July 31, 2002
September 4, 2002
September 25, 2002
November 6, 2002
November 20, 2002
December 12, 2002
January 8, 2003
March 6, 2003
May 29, 2003
September 18, 2003