Project Description: Refinish/replace classroom casework; ADA upgrades; remodel of administration; renovate multipurpose building to include new stucco, roofing, HVAC,  replace ceiling tiles, lights and mechanical grilles; replace doors throughout campus; upgrade master clock; upgrade intrusion alarm; reconfiguration of two classrooms into a new computer lab and library; and alterations to site and landscaping.

Project Funding:  The estimate construction cost include architect and engineering fees is $1.8 million.  This project is being funded from Measure B and Measure N.

Project Timeline: The project began in June 2007 and is scheduled for completion by the start of school.

School Front Landscape Plan:  PJS Landscape  (large PDF file)

School Site Before Pictures:
    August 2006
    April 2007

Project Progress Pictures:
    June 20, 2007
    July 2, 2007
    July 26, 2007
    August 2, 2007
    September 18, 2007
    October 25, 2007
    November 28, 2007