Project Description: Includes
the acquisition of approximately 10 acres of land and
the construction of an elementary school to include 25
classrooms, learning resource center, multipurpose room,
and administration.
Project Funding: The project construction cost was
$14.0 million and was funded from Measure B and the state building
program..
Project Timeline: The project began in
June 2005 and was complete by June 2006.
Project Progress Pictures:
Groundbreaking
Ceremony
July 13, 2005
August 30, 2005
September 12, 2005
November 22, 2005
February 1, 2006
March 26, 2006
April 5, 2006
June 1, 2006
June 6, 2006
July 15, 2006
Grand Opening Ceremony