Folsom Middle School
New Gymnasium, Wing A Renovation
and Site Work Renovation 2003
Project Description:
Renovation project includes HVAC;
replacement of interior finishes including floors, wall
surfaces and ceilings; installation of new equipment
including white boards, casework and cabinets; upgrading
of toilet rooms including accessibility toilets, sinks
and partitions; accessibility upgrades for ADA
compliance; repair and/or replacement of roofs as
needed; upgrade of electrical system and increase in
power capacity in classrooms to accommodate technology;
complete technology data system; increase network speed;
provide computers and LCD projectors and connect
portables to the local area network; installation of new
energy efficient lighting fixtures and controls; repair
of dry rot and termite damage; asbestos abatement;
relocate and refurbish existing portable buildings; and
replacement of old furniture. Gymnasium project
includes a new gymnasium complex consisting of a 14,000
square foot gymnasium with wood floor system, 2,600
square foot exercise room and 5,000 square foot of
locker, staff and storage areas. Site work project
includes construction of a new pedestrian and bicycle
path from the east side of the campus to the bike
storage area for safety; grading of the east portion of
the site, irrigation and landscaping to create a new 400
meter running track with a turf infield useable for
field sports; relocation of portable buildings to a
planned grouping near the rear of the campus; conversion
of a relocatable to a restroom near the play fields;
addition of parking near the multipurpose building;
extension of the student drop off lane; landscaping of
the center of the campus to provide walkways between the
buildings; extension of the automatic irrigation system
to portions of the campus currently without irrigation;
and addition of lighting at the interior of the campus.
Project Funding:
The project construction cost was
$10.0 million and was funded from Measure C and the state school building
program.
Project Timeline:
The project began in May 2002 and was complete by June 2003.
Project Progress Pictures:
May 28, 2002 Groundbreaking pictures
June 20, 2002
June 27, 2002
July 8, 2002
July 18, 2002
July 25, 2002
August 1, 2002
August 16, 2002
August 22, 2002
August 29, 2002
September 4, 2002
September 12, 2002 |
October 4, 2002
October 23, 2002
October 31, 2002
November 14, 2002
January 15,
2003
February 6,
2003
March 13,
2003
March 27,
2003
April 10,
2003
May 8,
2003
September 18,
2003
|
|