Project Description: Includes
an 18,600 square foot performing arts theater with 700
seats, full stage and support facilities; and athletic
stadium which includes football/soccer fields with
lighting, all-weather track, grandstands seating 5,000,
concessions and toilet building.
Project Funding:
The project construction cost was
$11.6 million and was funded from Measure C and the state school building
program.
Project Timeline:
The project began in June 2002 and was complete by October 2003.