Project Description:
Provide new asphalt shingle roofing; provide dedicated
male ADA accessible staff toilet room; expand
Administration and Nurse area (ADA Toilet Room upgrade);
provide Small Group Instruction room; update Library
lighting; renovate track and playfield; relocate and
replace bike rack; provide shade structure and benches;
provide new landscaping including shade trees; provide
new irrigation system; provide digital marquee sign;
replace chain-link fence with decorative iron fence
along streets; provide chain-link fence on property line
adjacent to neighbors in order to eliminate access;
replace old walkways to be ADA accessible; relocate c-tainers;
provide new asphalt hard courts and ball wall; provide
(2) full basketball courts; one with an 8’ hoop and one
with a 10’ hoop; provide (5) tetherball, 4-square,
hopscotch, kickball, circles, and (3) funnel ball;
provide new kindergarten building with (2) classrooms,
staff workroom, and (1) toilet room for each classroom;
replace one old relocatable building; provide hard
court, lawn, and apparatus areas; demolish existing
Multipurpose building and provide new modular building;
MP should contain restrooms, Cafeteria, Kitchen, Storage
and seating area for a minimum of 400 students; provide
PE Storage; provide enclosed delivery yard and trash
enclosure; provide staff parking lot; provide
Kindergarten drop-off and parking lot; and, provide
visitor parking and bus drop-off.
Project Funding:
The project construction cost is
$6.2 million and is funded from Measure N.
Project Timeline:
The project began in May 2009 and will complete by
November 2009.
Project Progress Pictures:
April 13, 2009
April 21, 2009
April 28, 2009
May 20, 2009
June 1, 2009
June 2, 2009
June 10, 2009
June 23, 2009
June 24, 2009
July 8, 2009
July 14, 2009
July 17, 2009
July 22, 2009
July 27, 2009
July 31, 2009
August 5, 2009
August 17, 2009
September 18, 2009
November
13, 2009
November 16, 2009
January 27, 2010
May 20, 2010