Project Description:
Includes
demolition and replacement of old portables;
installation of new fire alarm system; new intrusion
alarm system; new phone system for safety; new data
system for technology; replacement of HVAC system with
inclusion of energy management; addition of floor
covering, lights, casework, countertops, sinks,
ceilings, blinds, white boards, doors and hardware in
all rooms; upgrade of all areas for handicap
accessibility; repair and/or replacement of all roofs;
painting; provision of teaching station for music
program; provide traffic barrier between cafeteria and
parking lot; replacement of ball wall; installation of
remote irrigation control system; renovation of kitchen;
installation of cable television to classrooms;
eliminate exterior drain issues; and reconfigure
Reymouth classrooms.
Project Funding:
The project construction cost was
$4.0 million and was funded from Measure B and state building program.
Project Timeline:
The project began in February 2003 and was complete by
November 2003.
Project Progress Pictures:
March 10, 2003
March 24, 2003
April 7, 2003
May 16, 2003
June 20, 2003
July 8, 2003
July 14, 2003
July 24, 2003
August 14, 2003
August 15, 2003
January 22, 2004