Project Description:
Secure kindergarten playground, secure front of campus
with decorative iron fencing, create new bus drop off in
front of campus, replace old relocatable classrooms,
create a more visible location for the main office,
relocate programs from relocatables to permanent
structures or smaller office spaces on campus, remodel
main office spaces, including nurses room and workroom,
upgrade Computer lab and Library to new Learning
Resource Center (LRC), replace lighting in library,
upgrade restrooms and drinking fountains to current
code, replace intrusion alarm system with new Bosch
9412G addressable system, repairs and upgrades to campus
common areas, repairs to ball fields, and install new
fabric covered shade structure on existing playground.
Project Funding:
The estimated construction cost is
$2,200,000 and will be funded by Measure N.
Project Timeline: The project
will began in April 2008 and
should be completed by August 2008.
School Site Before Pictures:
April 2007
June 2, 2008
Project
Progress Pictures:
June
17, 2008
July 1, 2008
July 10, 2008
August 7, 2008
August 15, 2008
August 28, 2008