Project Description: Includes
abatement of blown-on acoustical asbestos ceiling;
installation of new lighting; replacement of the
gymnasium flooring; installation of new bleachers;
interior painting; new doors and hardware; acoustical
treatments and refinishing of the wrestling room floor.
Project Funding:
The project construction cost was
$1.2 million and was funded from Measure B.
Project Timeline:
The project began in March 2003 and was complete by
August 2003.
Project Pictures
Prior to Start of Work:
November 18, 2002
Project Progress Pictures:
April 8, 2003
May 16, 2003
June 3, 2003
June 16, 2003
June 24, 2003
July 8, 2003
July 11, 2003
July 15, 2003
July 21, 2003
August 5, 2003