Community Education Center
Parking Lot Expansion 2002
 

Project Description: Expansion and repaving of the parking lot.

Project Funding:  The project construction cost was $200,000 and was funded from Measure B.

Project Timeline:  The project began in July 2002 and was complete by August 2002.

Project Progress Pictures
    July 12, 2002 
   
July 22, 2002 
    July 29, 2002 
    August 12, 2002 

 